HARP Update: Water Quality Monitoring on the Ribble and Hodder
Many of you will have seen the early signs of activity around West Bradford on the Ribble and Newton-in-Bowland on the Hodder as work gets under way on the Haweswater Aqueduct Resi
The Hawes Water Resilience Programme (HARP) is a major, long-term infrastructure project being delivered by United Utilities to secure drinking water supplies across the North West of England.
The programme involves replacing sections of the historic Haweswater Aqueduct, which was constructed between the 1930s and 1950s and supplies water to millions of people. Parts of the aqueduct route pass beneath or close to sensitive landscapes and river catchments, including Bowland, the River Ribble, and the River Hodder.
The Ribble Fisheries Consultative Association (RFCA) represents angling clubs, riparian owners and fisheries interests across the Ribble and Hodder catchments, working in close collaboration with the Hodder Consultative (HC) and the Ribble Rivers Trust (RRT).
While the RFCA is not a regulatory authority, our members collectively manage important river and fishery assets. Our role in HARP has been to:
Note: This timeline is indicative only and subject to change. It has been provided to assist members and interested parties in understanding the current programme position.
The most significant construction impacts are not expected until late 2027, but early planning, monitoring and safeguards are being developed now.
Bowland:
Official Bowland information: https://harpinformation.co.uk/bowland/

Water quality monitoring has been a central focus of RFCA engagement throughout the HARP programme. Existing in-river monitoring sondes continue to be maintained and serviced, with new upgraded equipment due to be installed. These systems have already demonstrated their value, having helped identify and respond to non-HARP pollution incidents.
In parallel, the RFCA has worked in close collaboration with the Hodder Consultative (HC) and the Ribble Rivers Trust (RRT), alongside the Environment Agency and United Utilities, to support the development of a strong and reliable baseline water-quality dataset. This collaborative approach reflects a shared commitment to protecting the river environment
Although delays to the wider programme were not anticipated, they have allowed an extended period of monitoring, resulting in a robust benchmark dataset. This now provides a solid foundation for identifying abnormal readings at an early stage and supporting proportionate investigation where required.
As the project moves into the contractor-led phase with STRABAG, it is important that this monitoring approach is maintained and built upon to ensure continuity and confidence as works progress.
Alongside monitoring, the RFCA, HC and RRT have consistently stressed the importance of clear and practical emergency response arrangements. This includes agreed trigger points, well-defined communication routes and clarity around roles and responsibilities.
In practical terms:
“HARP – What This Means for RFCA Members” (1-page briefing)
Further Information

This page will be updated as the programme progresses and will form the basis of a dedicated HARP subsection on the RFCA website.