Many of you will have seen the early signs of activity around West Bradford on the Ribble and Newton-in-Bowland on the Hodder as work gets under way on the Haweswater Aqueduct Resilience Programme (HARP). RFCA recently attended a stakeholder meeting hosted by STRABAG, the project’s main contractor, alongside the Hodder Consultative, the Ribble Rivers Trust and the Environment Agency, to hear how water quality will be monitored as construction progresses. Here’s what we learned, and what we’re continuing to press for on behalf of everyone who fishes, walks or cares for our rivers.
You can view STRABAG’s full monitoring plans presentation from the meeting Ribble and Hodder Monitoring Plans 16-06-26 (1)
What is HARP?
What monitoring is already in place?
- Continuous ('live') sonde monitoring upstream and downstream of both crossing sites, on the main rivers.
- Quarterly water quality sampling for laboratory analysis – covering pH, electrical conductivity, turbidity and dissolved oxygen – at both sites.
- Additional quarterly sampling in the wider catchment, including Worston Brook (Ribble) and Foulscales Brook (Hodder).
- Invertebrate monitoring through the SmartRivers programme, carried out in Spring and Autumn at baseline, upstream and downstream locations on both rivers.
What’s proposed during construction?
- Continue live sonde monitoring upstream and downstream on the main rivers, with data continuing to be shared with third parties, including RFCA.
- Continue quarterly laboratory sampling at current locations, with additional sampling points on tributaries, subject to permit requirements still to be confirmed.
- Set trigger values for water quality parameters based on the baseline data currently being gathered, using a recognised methodology.
- Automatically alert STRABAG’s site and environmental teams if a trigger value is exceeded, with stakeholders then notified under STRABAG’s incident management process. Exactly how RFCA and others will be notified is still to be agreed.
What happens next?
- Additional sondes will be installed on both rivers this summer, with existing sondes relocated to cover the full extent of the sites. Data access will be briefly interrupted during this work.
- A follow-up meeting on the emergency response process is planned for August or September, including a site visit to the Hodder works.
- STRABAG is to confirm public right of way diversions at the Ribble crossing – relevant to walkers as well as anglers.
- On-site information signposts are being explored, to give the public easy access to project information and a way to report issues or incidents.
RFCA's position
These plans remain at an early stage and will be developed further through the environmental permitting process. RFCA, alongside the Hodder Consultative and the Ribble Rivers Trust, continues to engage with STRABAG and United Utilities to make sure the monitoring is robust and that anglers and the wider catchment community have access to clear, accurate information.